St. Pete Beach Publix Rebuild: Elevated 53,000 SF Store Set for 2029

The St. Pete Beach Publix will not return until mid-2029. Brixmor Property Group, owner of the fire-damaged Dolphin Village Shopping Center at 4655 Gulf Boulevard, told residents on Monday, November 23, 2026 that construction of a new 53,000-square-foot Publix and added retail space is expected to start in late 2027 and wrap up in mid-2029 (St. Pete Rising). The plans still need city approval (WTSP).
The timeline means St. Pete Beach could go roughly four years without its only full-service grocery store after the May 2025 fire that destroyed the previous store and several neighboring businesses (St. Pete Rising).
What Happened
Brixmor presented updated renderings, site plans and a development timeline at the first public informational meeting, a required step in the city's conditional use permit process (St. Pete Rising). The law firm representing Brixmor hosted the meeting (WTSP). Eighteen months after the fire, debris still covers the floor of the shuttered supermarket (St. Pete Rising).
The fire began at a neighboring CVS and spread to the Publix; the CVS building has since been demolished (WTSP). It struck while St. Pete Beach was still recovering from flooding caused by back-to-back hurricanes in 2024 (WTSP).
What Will Be Built
- Grocery: a 53,000-square-foot Publix, about 60% larger than the old 33,000-square-foot store and up from the 51,000 square feet Brixmor proposed in October 2025. Ryan Guheen, senior vice president of redevelopment at Brixmor, called it a new Publix store prototype (St. Pete Rising).
- Elevated store: to meet federal floodplain requirements, the supermarket will be raised over about 110 covered parking spaces, with elevator access for shoppers (St. Pete Rising).
- Parking: total center parking would rise from 490 to 592 spaces, though Brixmor may need a parking variance depending on the tenant mix (St. Pete Rising).
- Retail: about 5,000 square feet of replacement commercial space where CVS operated, plus two new freestanding 5,000-square-foot buildings along Gulf Boulevard near Starbucks that the city's development code requires (St. Pete Rising).
The new Publix and the commercial buildings are expected to come online at the same time in 2029 (St. Pete Rising). WTSP reported that Brixmor attributes the timeline to requirements to elevate the new Publix and neighboring businesses for protection against future hurricanes (WTSP).
Why It Is Taking So Long
Elise Batsel, an attorney with Stearns Weaver Miller representing Brixmor, said the planning process has involved working with FEMA on floodplain requirements, coordinating plans with Publix and resolving insurance matters from the fire. “We now have to comply with different requirements from FEMA, among other hurdles,” she said (St. Pete Rising).
Because the redevelopment exceeds 25,000 square feet in the city's Activity Center District, Brixmor needs a conditional use permit. It expects to submit its application early next year, followed by technical review and public hearings before the Planning Board and City Commission. The developer is targeting conditional use approval by mid-2027 and construction permits by the third quarter of 2027 (St. Pete Rising). Mayor Scott Tate told residents the city “will not do anything to slow this down” (St. Pete Rising).
Tenants Feel the Gap
Businesses still open at the nearly 60-year-old center include Starbucks, Chick-fil-A, Chase, Jersey Mike's, Playa Bowls, Beach Vibe Cycle Rentals, Top Shape Gym and Violet's Beachside Ice Cream (St. Pete Rising). Jerry Zamudio, owner of Beach Vibe Cycle Rentals, told WTSP that foot traffic has dropped and that he had to renegotiate his lease, and Sam Tran, manager of Noire The Nail Bar, said business has slowed but welcomed the prospect of Publix returning (WTSP).
Batsel said the project is intended to be built in a single phase, though work may happen at different times, and that a construction management plan will be prepared later. Brixmor plans to meet separately with existing tenants (St. Pete Rising).
Implications for Owners, Developers, Contractors and Subs
- Flood rules now shape retail design. An elevated grocery over a parking deck on a barrier island means structural concrete, elevators and flood-resistant construction below the store level, a different scope from a typical slab-on-grade box.
- Entitlements set the schedule. With conditional use approval targeted for mid-2027 (St. Pete Rising), most of the delay is in planning and permitting, not construction. Owners rebuilding after a disaster should budget time for FEMA coordination.
- Phasing around open tenants. Building while restaurants, a bank and shops stay open will require site logistics, access and signage planning that the construction management plan must address (St. Pete Rising).
- Grocery anchors keep investing in Florida. Publix is also expanding its distribution network, as WCG covered in the $200 million Publix Lakeland warehouse expansion.
Pinellas County has several other projects working through local approvals, including Ease on 5th in south St. Petersburg.
What to Watch
- Brixmor's conditional use application, expected early in 2027 (St. Pete Rising).
- Planning Board and City Commission hearings, and any parking variance request.
- Selection of a contractor and the construction management plan.
Bottom Line
Brixmor plans an elevated 53,000-square-foot Publix and new retail at Dolphin Village in St. Pete Beach, with construction from late 2027 to mid-2029. City approval is still required, and floodplain rules, insurance and permitting explain most of the wait.
Key Questions
When will the St. Pete Beach Publix reopen?
Brixmor expects construction of the new Publix at Dolphin Village in St. Pete Beach to begin in late 2027 and finish in mid-2029; an official opening date has not been announced (St. Pete Rising).
How big will the new St. Pete Beach Publix be?
The new Publix at Dolphin Village will be 53,000 square feet, about 60% larger than the previous 33,000-square-foot store (St. Pete Rising).
Why is the St. Pete Beach Publix elevated?
The St. Pete Beach Publix will be elevated to comply with federal floodplain requirements, with about 110 covered parking spaces below the store (St. Pete Rising).
Who owns Dolphin Village in St. Pete Beach?
New York-based Brixmor Property Group owns the Dolphin Village Shopping Center at 4655 Gulf Boulevard in St. Pete Beach (St. Pete Rising).
Related Coverage
- Publix Lakeland Warehouse Expansion: $200M Produce Center Advances
- Ease on 5th: St. Pete Approves $2.2M for 71 Affordable Apartments
- U.S. 19 Construction in Pinellas Pushed to 2030 as County Adds $10M Utility Deal
Image credit: Brixmor rendering, via St. Pete Rising. Image from the source article.
Sources
- St. Pete Rising, St. Pete Beach Publix not expected to return until mid-2029, four years after devastating fire, https://stpeterising.com/home/owner-of-fire-damaged-st-pete-beach-plaza-takes-next-steps-to-rebuild-center-with-larger-publix-and-new-retail
- WTSP via Yahoo News, Publix at St. Pete Beach's Dolphin Village is not expected to reopen until 2029, https://www.yahoo.com/news/articles/publix-st-pete-beach-dolphin-082939038.html