Skanska Data Center Georgia: $275M Award for a New 48 MW Building

Skanska has another data center in Georgia. The Swedish contractor said on November 26, 2026 that it signed an additional award worth $275 million, about SEK 2.8 billion, with an existing, unnamed client to build a new 48 MW data center in Georgia (Skanska). Construction began in November and is scheduled to finish in October 2028 (Skanska).
The contract will be counted in Skanska’s U.S. order bookings for the fourth quarter of 2026 (Skanska), and Investing.com reported the same terms the morning of the announcement (Investing.com).
What Happened
Skanska’s scope covers a building of about 244,730 square feet, or roughly 22,700 square meters, including the shell and interior fit-out of technical spaces, support areas and offices (Skanska). The award also includes an ancillary water treatment building of about 860 square feet (Skanska).
As with Skanska’s earlier Georgia awards, the release does not name the client, the city or county, or the site, and it does not describe power supply arrangements (Skanska). It also does not say whether the new building is on the same campus as Skanska’s other Georgia data center work.
Skanska’s Run of Georgia Data Center Awards
This is at least the third Georgia data center contract Skanska has announced in 2026, each with an existing client:
- First quarter: a $75 million award, about SEK 690 million, for a data center of about 244,090 square feet with site work, underground utilities, administration space and five data halls. Construction started in March 2026, with completion expected in the first quarter of 2028, and the order was booked in the first quarter (Skanska).
- Second quarter: a $255 million supplemental contract, about SEK 2.3 billion, for a 22,700 square meter data center with site work, underground utilities, administration space and five data halls, on the same March 2026 to first quarter 2028 schedule (Skanska).
- November: the new $275 million, 48 MW award, running from November 2026 to October 2028 (Skanska).
The company also booked a much larger order in August: about $1.2 billion to build four data center buildings totaling roughly 808,000 square feet in the southeastern United States for an unnamed existing customer, with construction from the third quarter of 2026 to the third quarter of 2028 (The Next Web). The Next Web called it the largest single data center order Skanska has announced and listed other 2026 U.S. awards, including a $238 million follow-on in Virginia and a $94 million second building on another Virginia campus (The Next Web). Skanska has not said whether the August order includes any Georgia sites.
These orders helped push Skanska’s construction backlog to a record at the end of September, as WCG reported in Skanska Q3 2026 Report: Record SEK 328 Billion Backlog.
A Mixed Data Center Market
The award comes as the broader data center market sends mixed signals. Data center construction starts fell to $9.4 billion in September, as WCG covered in Data Center Construction Starts Fall to $9.4B in September, and local opposition stopped twice as many projects in the third quarter as a year earlier, according to WCG’s report on Relae’s Q3 data. Contractors with data center work have also reported longer backlogs than those without it, as shown in ABC’s October backlog data.
Against that backdrop, all three of Skanska’s Georgia orders are follow-on work for existing clients, a sign that at least some owners are continuing phased buildouts (Skanska) (Skanska) (Skanska).
Implications for Owners, Developers, Contractors and Subs
- Repeat clients drive the volume. Every Skanska data center award cited here went to an existing client (Skanska) (The Next Web). Subcontractors that perform well on a first building are positioned for the follow-on phases.
- Two-year MEP-heavy schedules. A 48 MW building with a November 2026 to October 2028 schedule (Skanska) points to sustained demand for electrical, mechanical, controls and commissioning crews in Georgia through 2028.
- Water scope is part of the package. The separate water treatment building (Skanska) shows that water systems can be packaged into the main data center contract rather than bid separately.
- Labor competition in the Southeast. Several large builds running on overlapping 2026 to 2028 schedules (Skanska) (The Next Web) will compete for the same skilled trades across Georgia and neighboring states.
What to Watch
- Skanska’s fourth-quarter 2026 report, which will include this order (Skanska).
- Any disclosure of the client, location or power supply for the Georgia buildings.
- Further follow-on awards on the same campuses.
Bottom Line
Skanska signed a $275 million award for a 48 MW, 244,730-square-foot data center in Georgia for an existing client, with construction running from November 2026 to October 2028. It is the company’s third announced Georgia data center contract of 2026 and adds to a record backlog built largely on U.S. data center work.
Key Questions
How much is Skanska’s new Georgia data center contract?
Skanska’s new Georgia data center award announced November 26, 2026 is worth $275 million, about SEK 2.8 billion (Skanska).
How big is the Skanska Georgia data center?
The Skanska Georgia data center is a 48 MW building of about 244,730 square feet, plus an 860-square-foot water treatment building (Skanska).
When will the Skanska Georgia data center be finished?
Construction on the Skanska Georgia data center began in November 2026 and is scheduled to be completed in October 2028 (Skanska).
Who is the client for the Skanska Georgia data center?
Skanska has not disclosed the client for the Georgia data center, describing it only as an existing client (Skanska).
Related Coverage
- Skanska Q3 2026 Report: Record SEK 328 Billion Backlog Led by U.S. Data Centers
- Contractor Backlog Falls to 8.1 Months in October as Data Center Gap Widens
- Data Center Cancellations Double in Q3 2026 as Local Officials Say No
- Data Center Construction Starts Fall to $9.4B in September as Costs Climb 31%
Image credit: Taylor Vick on Unsplash (Unsplash License). Free-license photo of data center network cabling; the Skanska release did not include a usable image.
Sources
- Skanska via PR Newswire, Skanska signs an additional award to build data center in Georgia, USA, worth USD 275M, about SEK 2.8 billion, https://prnewswire.com/news-releases/skanska-signs-an-additional-award-to-build-data-center-in-georgia-usa-worth-usd-275m-about-sek-2-8-billion-302951071.html
- Investing.com, Skanska wins $275 mln data center contract in Georgia, USA, https://uk.investing.com/news/stock-market-news/skanska-wins-275-mln-data-center-contract-in-georgia-usa-93CH-5005323
- The Next Web, Skanska takes a $1.2bn order to build four US data centres for an unnamed client, https://thenextweb.com/news/skanska-1-2bn-four-data-centres-southeast-usa
- Skanska, Skanska signs additional contract for data center in Georgia, USA, worth USD 255M, about SEK 2.3 billion, https://www.skanska.com/group/en/media/press-releases/2026/skanska-signs-additional-contract-for-data-center-in-georgia-usa-worth-usd-255m-about-sek-2.3-billion
- Skanska, Skanska builds data center in Georgia, USA for USD 75M, about SEK 690M, https://www.skanska.com/group/en/media/press-releases/2026/skanska-builds-data-center-in-georgia-usa-for-usd-75m-about-sek-690m