Coast Guard Academy STEM Building: Whiting-Turner Wins $155M Contract

Aerial photo of the U.S. Coast Guard Academy waterfront campus in New London, Connecticut | Westside Construction Group
Aerial photo of the U.S. Coast Guard Academy waterfront campus in New London, Connecticut | Westside Construction Group

The Coast Guard Academy STEM building is under contract. The U.S. Coast Guard awarded The Whiting-Turner Contracting Co. a $155 million design-build-to-budget contract on November 16, 2026 for STEM West, a new science, technology, engineering and mathematics facility of about 120,000 square feet at the U.S. Coast Guard Academy in New London, Connecticut (U.S. Coast Guard via MilitarySpot). Construction is expected to finish in spring 2030 (U.S. Coast Guard via MilitarySpot) (Construction Dive).

The Coast Guard said the award came one month ahead of schedule (U.S. Coast Guard via MilitarySpot). The building will house the academy’s chemistry, naval architecture and marine engineering, and civil and environmental engineering programs (U.S. Coast Guard via MilitarySpot).

What Happened

The contract went to Whiting-Turner, which the Coast Guard’s announcement lists as based in Greenbelt, Maryland (U.S. Coast Guard via MilitarySpot) and Construction Dive describes as Baltimore-based (Construction Dive). STEM West will include laboratories, classrooms and design spaces (Construction Dive). Because the contract is design-build-to-budget, stakeholder input will be folded in as the final design is completed (U.S. Coast Guard via MilitarySpot). Neither source named the design firm on Whiting-Turner’s team.

Superintendent Rear Adm. Greg Rothrock said the investments strengthen the academy’s ability “to educate, develop and prepare the next generation” of Coast Guard officers (U.S. Coast Guard via MilitarySpot).

Waesche Hall Renovation

The same announcement covered a second award. On September 29, the Coast Guard awarded Healtheon Inc. of New Orleans a $29.3 million contract to repair, renovate and reconfigure Waesche Hall, with completion expected in May 2029 (U.S. Coast Guard via MilitarySpot). The work will modernize about 40,000 of the building’s 60,000 square feet (U.S. Coast Guard via MilitarySpot):

  • Repairs to bathrooms, faculty offices, classrooms, bookshelves and the Admissions Department.
  • A reconfigured first-floor museum exhibit area with a projection screen and temporary foldable seating.
  • Three new classrooms on the second floor, plus library space, offices and academic department space.

The Wider Academy Program

Both projects are funded through the Working Families Tax Cuts Act, and the Coast Guard has obligated $20 billion of the nearly $25 billion it received under that law (U.S. Coast Guard via MilitarySpot). Construction Dive noted that the law is also known as the “One Big Beautiful Bill” and cited the Senate Commerce Committee in calling the $25 billion the largest Coast Guard investment ever (Construction Dive).

The academy modernization also includes a new aquatics center, a parking garage and improvements to cadet living conditions in Chase Hall (U.S. Coast Guard via MilitarySpot). In August, the Coast Guard awarded a $51 million contract to renovate Chase Hall Annex A (U.S. Coast Guard via MilitarySpot), which also went to Whiting-Turner (Construction Dive). Founded in 1876, the academy is one of five federal service academies and commissions about 200 officers a year (U.S. Coast Guard via MilitarySpot).

Whiting-Turner has a run of Coast Guard work elsewhere, including $137 million in berth upgrades at Base Seattle and a $69 million design-build of two hangars at Air Station Barbers Point in Hawaii, plus $173.7 million in additional Base Seattle work in September 2026 (Construction Dive). WCG has followed the agency’s shore program in Coast Guard Awards $612 Million in Base Construction and Tutor Perini Unit and Skanska Win $586 Million in Coast Guard Pier Contracts.

Implications for Owners, Developers, Contractors and Subs

  • Lab-heavy MEP scope. Chemistry and engineering labs typically mean fume hoods, specialty exhaust, lab gases and dense electrical and controls work, which puts mechanical and electrical subs at the center of the job.
  • Design-build-to-budget sets the price first. With the budget fixed at $155 million (U.S. Coast Guard via MilitarySpot), design decisions will be made to fit the number, so trade partners brought in early can influence systems and sequencing.
  • Work on an active campus. STEM West, Waesche Hall and the Chase Hall work will overlap with academic operations, so logistics, phasing and security access will matter.
  • More federal shore work is coming. With $20 billion already obligated out of nearly $25 billion (U.S. Coast Guard via MilitarySpot), contractors and subs in New England and other coastal markets should watch for more Coast Guard solicitations.

What to Watch

  • Final design for STEM West and subcontract buyout by Whiting-Turner.
  • Awards for the planned aquatics center and parking garage.
  • Progress on the Waesche Hall renovation ahead of its May 2029 target.

Bottom Line

The Coast Guard has hired Whiting-Turner under a $155 million design-build-to-budget contract for STEM West, a 120,000-square-foot academic building at the Coast Guard Academy in New London, due in spring 2030. It is part of a broader academy modernization funded through the Working Families Tax Cuts Act.

Key Questions

Who is building the Coast Guard Academy STEM building?

The Whiting-Turner Contracting Co. won the $155 million design-build-to-budget contract for STEM West at the U.S. Coast Guard Academy in New London (U.S. Coast Guard via MilitarySpot).

How big is the Coast Guard Academy STEM West building?

STEM West at the Coast Guard Academy will be about 120,000 square feet, with laboratories, classrooms and design spaces (Construction Dive).

When will the Coast Guard Academy STEM building be finished?

Construction of STEM West at the Coast Guard Academy is expected to finish in spring 2030 (U.S. Coast Guard via MilitarySpot).

How is the Coast Guard Academy STEM building funded?

STEM West and the Waesche Hall renovation are funded through the Working Families Tax Cuts Act, which provided the Coast Guard nearly $25 billion (U.S. Coast Guard via MilitarySpot).

Related Coverage

Image credit: Petty Officer 3rd Class Matthew Thieme, U.S. Coast Guard, via DVIDS (public domain), as credited in the Construction Dive source article. Image from the source article.

Sources

Share

Let's connect

For organizations planning commercial, industrial, or infrastructure work, we will review the project and recommend the appropriate delivery approach.

Join our team

If you hold yourself to careful, accountable work, you already work the way we do.