Update: X-energy's third quarter 2026 results, released November 12, 2026, report that vertical construction of the shell of its TX-1 nuclear fuel plant in Oak Ridge, Tennessee was completed on schedule in the quarter, and that the company has selected Fluor for nuclear island engineering on Energy Northwest's Cascade project in Washington (X-energy). The update follows WCG's earlier report on the start of above-ground construction at TX-1.

What Happened

X-energy, the developer of the Xe-100 high-temperature gas-cooled small modular reactor and its TRISO-X fuel subsidiary, reported total revenues and grant income of $66.3 million for the three months ended September 30, 2026, up from $30.4 million a year earlier. Services revenue was $51.5 million and grant income was $14.8 million (X-energy).

The consolidated net loss was $83.7 million, of which $59.4 million was attributable to X-energy, Inc., compared with a net loss of $219.0 million in the third quarter of 2025 (X-energy). CEO J. Clay Sell said the team is building momentum as it deepens relationships with leading energy and industrial companies (X-energy).

Construction Milestones

TX-1 Fuel Plant, Oak Ridge

Vertical construction of the TX-1 facility shell was completed on schedule in the third quarter. The next phase covers interior buildout, fuel fabrication equipment installation and supporting facilities (X-energy). Once operating, the plant is expected to produce about 700,000 TRISO-X fuel pebbles a year, or 5 metric tons of uranium, enough to fuel up to 11 Xe-100 reactors. The Nuclear Regulatory Commission granted TRISO-X a 40-year Special Nuclear Material License for the facility earlier in 2026 (X-energy). The release does not give a date for the start of operations.

For context, WCG's November 2025 report on TX-1 described a 214,812 square foot facility on a 110-acre site at the Horizon Center in Oak Ridge, with Clark Construction Group holding a $48.2 million core and shell award and the shell phase targeted for completion by mid-2026. The third quarter update, which reports the shell finished on schedule, is consistent with that target. It also means the project is moving from the structural and envelope trades to the more specialized and usually longer interior phase, where process piping, ventilation and filtration systems, fire protection, instrumentation and the fuel fabrication lines themselves have to be installed, tested and documented to nuclear quality standards before the plant can produce fuel. The release does not say who will perform that interior work or what it will cost.

Long Mott, Seadrift, Texas

The NRC approved the construction permit for the Long Mott project that Dow and X-energy are developing at Dow's Seadrift Operations site, which would supply zero-carbon electricity and high-temperature steam to the chemical complex. Dow and X-energy announced the approval on November 9, 2026. The company says it is the first NRC construction permit for a high-temperature gas-cooled reactor in nearly 60 years and the first for a pebble-bed design, and Sell said it was received more than a month ahead of schedule (X-energy). The project is part of the Department of Energy's Advanced Reactor Demonstration Program. The release does not give a construction start date.

Cascade, Washington, and Indiana

Fluor will provide nuclear island engineering and design services for Energy Northwest's Cascade Advanced Energy Facility near Richland, Washington, its second commercial nuclear island contract with X-energy after Long Mott (X-energy). X-energy also signed a joint development agreement with AEP to study a proposed 960 MW, 12-unit Xe-100 plant in Sullivan County, Indiana, with Amazon funding part of the development work (X-energy).

The company placed its first steam generator component procurement order with Alleima and Doosan Enerbility, and the Xe-100 was accepted into the United Kingdom's Generic Design Assessment, a process expected to take about three years, pursued with Centrica (X-energy).

Spending and Balance Sheet

Capital expenditures for the first nine months of 2026 were $178.1 million, offset by $80.0 million in government grant reimbursements, for net spending of about $98.1 million. Capital spending rose $98.8 million from a year earlier, driven by facility construction (X-energy). At September 30, X-energy had $1,044.1 million in cash and equivalents, $514.3 million in short-term investments and $247.1 million in long-term investments, for total liquidity of $1,805.5 million, and no debt outstanding (X-energy).

X-energy counts 144 expected reactors across four announced projects, about 11.5 GW of electric capacity, assuming customers fully exercise contingent rights. The release does not disclose a backlog figure (X-energy).

Implications for Owners, Developers, Contractors and Subs

  • TX-1 moves to the interior trades. With the shell done, work at Oak Ridge shifts to process equipment, mechanical, electrical, controls and nuclear-grade finishes. That is where specialty subcontractors with clean room and process experience fit.
  • Long Mott is now permitted. An approved construction permit turns a Gulf Coast industrial site into a likely large nuclear construction job. Contractors in Texas should watch for site work and early package procurement.
  • Engineering is being placed. Fluor's second nuclear island contract signals that design for Cascade is moving. Construction packages typically follow engineering by a year or more.
  • Industrial owners as customers. Dow's use of reactor steam and Amazon's funding role show that industrial and data center owners, not just utilities, are driving new nuclear demand, much like the Constellation and Google uprate deal.

What to Watch

  • A construction start date and contractor selections for Long Mott.
  • Equipment installation progress and an operating date for TX-1.
  • Feasibility results from the AEP Indiana study.
  • Progress in the United Kingdom Generic Design Assessment, which X-energy expects to take about three years, and any site announcements with Centrica (X-energy).
  • Further steam generator and component orders after the first procurement with Alleima and Doosan Enerbility, which would show how much of the supply chain is being placed in North America.
  • X-energy's next investor appearances, including UBS on November 30 and Truist and Stifel on December 10, 2026 (X-energy).

Bottom Line

X-energy's third quarter shows its projects moving from paper to physical work: the TX-1 fuel plant shell is finished, Long Mott has its construction permit, and engineering for a second commercial plant is under contract. For construction firms, the advanced nuclear pipeline is becoming real work in Tennessee, Texas and Washington, even as the company has not yet published construction start dates.

Key Questions

What is the status of the X-energy TX-1 fuel facility in Oak Ridge?

X-energy said in its November 12, 2026 results that vertical construction of the TX-1 shell in Oak Ridge, Tennessee was completed on schedule in the third quarter, and interior buildout and equipment installation are next (X-energy).

Did X-energy's Long Mott project get an NRC construction permit?

Yes. The NRC approved the construction permit for the Dow and X-energy Long Mott project at Seadrift, Texas, announced on November 9, 2026 (X-energy). A construction start date has not been disclosed.

What were X-energy's third quarter 2026 results?

X-energy reported $66.3 million in revenues and grant income and a consolidated net loss of $83.7 million for the quarter ended September 30, 2026, with total liquidity of $1,805.5 million and no debt (X-energy).

Who is engineering the Cascade Xe-100 project in Washington?

X-energy selected Fluor for nuclear island engineering and design on Energy Northwest's Cascade Advanced Energy Facility near Richland, Washington (X-energy).

Related Coverage

Image credit: X-energy. Image from the source article.

Sources

Share

Let's connect

For organizations planning commercial, industrial, or infrastructure work, we will review the project and recommend the appropriate delivery approach.

Join our team

If you hold yourself to careful, accountable work, you already work the way we do.