ROC City Skatepark Expansion Opens as New York’s Largest Concrete Skatepark

Officials cut the ribbon on the ROC City Skatepark Phase II expansion in Rochester | Westside Construction Group
Officials cut the ribbon on the ROC City Skatepark Phase II expansion in Rochester | Westside Construction Group

The ROC City Skatepark expansion is complete. State and city officials cut the ribbon on Monday, November 23, 2026 on the $4.7 million second phase of the park along the Genesee River in downtown Rochester, which officials say makes it the largest concrete skatepark in New York State (13WHAM). Mayor Malik Evans also said a third phase is planned, and Spectrum News reported that City Council recently approved buying land for it (Spectrum News).

What Happened

The ribbon cutting marked the opening of Phase II, which adds more than 20,000 square feet of skateable space and extends the park under the I-490 overpass, roughly doubling its size (Spectrum News). The park sits beneath the Frederick Douglass-Susan B. Anthony Bridge on South Avenue and is part of the city’s ROC the Riverway program (News10NBC). The New York Department of State and the City of Rochester jointly announced the completion (13WHAM).

Evans said in a statement that the investment will bring people together, keep activating the waterfront and give people more reasons to come downtown (13WHAM). City Council member Mitch Gruber pointed to the creative reuse of land under the bridge that he said had been dead for years (News10NBC). Erich Lehman of Friends of the Roc City Skatepark said riders will travel from far away to use it (Spectrum News).

What Is Confirmed

  • Cost and funding: a $4.7 million expansion supported by $3 million from the state’s Local Waterfront Revitalization Program (13WHAM), paid through the state Environmental Protection Fund (Spectrum News). The balance combined city capital funds with the state grant (13WHAM).
  • Scope: new street-style features, beginner-friendly areas, improved accessibility and space for events, competitions and lessons (13WHAM), plus added lighting (News10NBC).
  • Total size: about 35,000 square feet of skateable space, passing High Bridge Skatepark in New York City at about 30,000 square feet (WXXI News).
  • Builder: both phases were built by Seattle-based Grindline (WXXI News).
  • Hours: the park is open daily from 6 a.m. to 10 p.m. (Spectrum News).

How the Project Got Here

Phase I opened in 2020 with 14,300 square feet of skate area and $1 million in state funding through ROC the Riverway (Spectrum News). State and city leaders broke ground on Phase II on October 16, 2025, with completion planned for fall 2026 (Spectrum News).

The work moved quickly. In July, WXXI reported that crews were well ahead of a projected spring 2027 finish, and city senior landscape architect Jeff Mroczek said the team had expected completion the following spring (WXXI News). The site is unusual: the land under the bridge is owned by the state Department of Transportation, and the city partnered with the agency to turn what Mroczek described as a rubble pit into public space with natural cover from rain (WXXI News).

The design changed between phases. Phase I leaned on steep banks, high quarter pipes and a nine-foot-deep bowl, while Phase II is a street plaza with rails, banks, pyramids and paved areas for DJ booths or judge tables (WXXI News).

What Is Not Yet Known

Reported costs vary. Spectrum News describes the expansion as more than $4 million (Spectrum News), 13WHAM puts it at $4.7 million (13WHAM), and WXXI described the overall skatepark project as costing nearly $8 million (WXXI News). For Phase III, Evans said it will add seating and competition space (News10NBC), but no budget, design team or schedule has been announced, and the price of the land Council approved was not reported.

What It Means for Owners and Contractors

  • Another ROC the Riverway project delivered. The skatepark joins the $8.2 million Genesee Crossroads Park work and the High Falls State Park groundbreaking in a steady run of public waterfront projects downtown.
  • Early finish on a public job. Finishing months ahead of the earlier projection shows what a specialty builder with repeat experience on a site can deliver. Owners planning similar parks may weigh specialty contractors for poured concrete recreation work.
  • Building under state infrastructure. Work beneath an interstate overpass and a state bridge on DOT land requires coordination with the state agency, and later phases will likely carry the same requirements.
  • Phase III is the next opportunity. With land approved, site work, concrete, lighting and seating packages could follow once the city sets funding and design.

What to Watch

  • A cost, funding source and design team for Phase III.
  • Whether the state awards further Local Waterfront Revitalization Program money to Rochester riverfront projects.
  • Events and competitions at the new competition area.

Key Questions

Is the ROC City Skatepark expansion open?

Yes. Rochester and the New York Department of State marked the completion of the ROC City Skatepark’s $4.7 million Phase II expansion with a ribbon cutting on Monday, November 23, 2026 (13WHAM).

Is ROC City Skatepark the largest skatepark in New York?

The city says the expanded ROC City Skatepark in Rochester is the largest concrete skatepark in New York State (Spectrum News), with about 35,000 square feet of skateable space (WXXI News).

Who paid for the ROC City Skatepark expansion?

The $4.7 million Rochester expansion received $3 million from New York’s Local Waterfront Revitalization Program, with the rest covered by city funds (13WHAM).

Will there be a Phase III at ROC City Skatepark?

Mayor Malik Evans said a third phase of the Rochester skatepark with more seating and competition space is planned; no cost or schedule has been announced (News10NBC).

Related Coverage

Image credit: Mark Schuman, WHAM. Image from the source article.

Sources

Share

Let's connect

For organizations planning commercial, industrial, or infrastructure work, we will review the project and recommend the appropriate delivery approach.

Join our team

If you hold yourself to careful, accountable work, you already work the way we do.