Tropicana Field, the St. Petersburg stadium whose roof was torn off by Hurricane Milton in October 2024, is hosting World Series games this week after a city led repair program that came in at $58 million, below the $59.7 million the City Council approved, Bay News 9 reported on October 22, 2026 (Bay News 9).
The Tampa Bay Rays are scheduled to host the Milwaukee Brewers at the Trop on Monday, Tuesday and, if needed, Wednesday. For the construction side of the story, the series is the public payoff on a closely watched storm recovery job: a full fabric roof replacement completed on a deadline that the team's former ownership had argued could not be met (Bay News 9).
What Happened
After the 2024 storm, the stadium's roof was gone and the field was covered in debris, but the structure, seating, concourses and clubs were intact, according to City Development Administration Managing Director Beth Herendeen, who oversaw the project. The City Council approved $59.7 million in repairs, and the final cost came in at $58 million. FEMA, insurance and state grants together covered more than half of the cost, though Bay News 9 did not report the individual amounts (Bay News 9).
Herendeen said the job "took a lot of people a lot of time, energy, blood, sweat and tears to get it done." The repairs included installing 24 new roof panels. She said the roof material was fabricated in Germany and assembled in China before being flown in, and that a volcanic eruption that closed airspace over the North Pole delayed delivery of the first panels (Bay News 9).
How the Roof Was Rebuilt
Earlier reporting by Facilities Dive detailed the work. AECOM Hunt led the project with local contractor Hennessey Construction as a partner. Kenneth Johnson, AECOM Hunt's executive vice president of sports, said he called the city within 48 hours of the storm and his team was on site within 72 hours (Facilities Dive).
- The new roof uses about 400,000 square feet of PTFE coated fiberglass fabric made by Germany's Verseidag-Indutex, rated for hurricane force winds up to 165 mph.
- Individual panels are 360 feet long and were sewn in China to match the stadium's existing cable system.
- The team located the original 1990s engineered drawings on site and used 3D scans and drone surveys to document the cable geometry.
- Crews began placing the roof in August 2025 and finished in November 2025. The project also restored water damaged areas and added amenities such as bars.
Johnson said the hardest part of the roof work was the damage assessment and called the finished facility "the best it's looked in 30 years." Facilities Dive put the project cost at roughly $60 million, while the city's final figure reported by Bay News 9 is $58 million (Facilities Dive; Bay News 9).
Where Things Stand
- The Rays returned to the Trop for the 2026 home opener after one season at Steinbrenner Field in Tampa (Facilities Dive).
- The city is obligated to provide the stadium to the team through at least the 2028 season, according to Facilities Dive, citing St. Pete Rising.
- The Rays have announced plans for a new ballpark in Tampa that they aim to open by the 2029 season. We have followed that project's approvals in Tampa Council Reverses Course, Approves Rays Stadium Bond Validation Step.
- City Council Chair Lisset Hanewicz said, "Together, we fulfilled our commitment, met the tight timeline, and welcomed baseball back to our city" (Bay News 9).
Implications for Owners, Developers, Contractors and Subs
For public owners: The Trop shows what a fast storm recovery can look like when an owner commits early, layers FEMA, insurance and state grant money, and engages a contractor within days. The project finished under the approved budget despite an international supply chain for the roof membrane.
For contractors: Long lead specialty materials drove the schedule. Fabric fabricated in one country and sewn in another left little float, and an unexpected airspace closure still caused delays. On any recovery job with custom materials, early procurement and backup logistics plans are essential.
For local businesses and developers in downtown St. Petersburg: Bar owner Pete Boland told Bay News 9, "There's a frenetic energy downtown now," pointing to the economic value of keeping the stadium active while long term redevelopment plans for the area take shape.
What to Watch
- Whether the city publishes final reimbursement figures from FEMA, insurance and the state.
- Long term plans for the Tropicana Field site once the team moves to its new ballpark.
- Progress on the Rays' new stadium in Tampa and its construction procurement.
Bottom Line
A stadium that lost its roof two years ago is now hosting the World Series. The $58 million repair, led by AECOM Hunt with Hennessey Construction, is a useful case study in hurricane recovery for Florida owners and builders, and it keeps a major downtown St. Petersburg venue active through at least 2028.
Related Coverage
- St. Petersburg Gets $173M in Milton Recovery Funds After Federal Error Is Fixed
- Tampa Council Reverses Course, Approves Rays Stadium Bond Validation Step
- Rays Plan Westshore Experience Center as Stadium Trade Outreach Draws 400
- America's Sports Venue Construction Wave: Titans Stadium, OKC Arena, and a Las Vegas Ballpark Reshape the Industry
Image credit: Spectrum Bay News 9. Image from the source article.
Sources
- Bay News 9, "Tropicana Field will host the World Series after $58 million in repairs": https://baynews9.com/fl/tampa/news/2026/10/22/tropicana-field-will-host-the-world-series-after--million-in-repairs
- Facilities Dive, "How AECOM Hunt raced to replace Rays' $60M ballpark roof": https://www.facilitiesdive.com/news/aecom-hunt-replace-rays-ballpark-roof-construction-stadium/816809/