Pulse Memorial Construction Set to Start in Orlando on $12.6M Contract

Pulse memorial construction is set to become visible at the former nightclub site in Orlando this month, the City of Orlando said in a November 10, 2026 update, with Winter Park based Gomez Construction preparing to mobilize on the $12.6 million project after receiving a notice to proceed on October 13 (WFTV).
What Happened
According to the city update, the contractor has spent the weeks since the notice to proceed finalizing subcontractor agreements, securing permits and preparing to mobilize. City spokesperson Ashley Papagni said mobilization is expected to begin in November, with activity becoming visible in the coming weeks. The city is not holding a formal groundbreaking ceremony (WFTV).
Central Florida Public Media, in a report carried by WUSF on November 12, said Gomez Construction received formal authorization to proceed in October and has been finalizing permits, contracts and preparations, and that the city expects visible construction within the next few weeks, with completion expected in 2027 (WUSF).
The memorial will honor the 49 people killed in the June 12, 2016 shooting at Pulse, along with survivors, victims' families and others affected. The city describes it as a place for remembrance, reflection and healing (City of Orlando).
The Contract and the Budget
The Orlando City Council voted unanimously on October 12 to move forward with construction, approving a $12.6 million contract with Gomez Construction. The council had selected Gomez in July 2025, when it scored highest of three bidding firms (WUSF). The city's project page lists the budget at $12,600,000 and classifies the work as a capital improvement infrastructure project (City of Orlando).
Funding comes from several public and private sources. The City of Orlando has budgeted $7.5 million, the Orange County Commission pledged $5 million in June 2025, and the Florida Legislature awarded more than $394,000 in grant funding in 2025 (WUSF). Individual donations and community partners, including Walt Disney World, Orlando Health and the DeVos Family Foundation, are also contributing (WUSF).
Getting to that number took value engineering. City spokesman Douglas Richards said Gomez provided a cost estimate at each design milestone along with ideas to save money, and many of the savings came from switching suppliers. Changes from earlier designs included replacing a tile mosaic on the visitors center's curved wall with stucco, swapping granite on the survivor walls for tile, removing benches outside the visitors pavilion, replacing copper plumbing with PVC, cutting plant sizes by roughly half and moving paver supply from an out of state company to a local one. Even so, the project was still over budget on lighting and electrical work at the time of the October vote (WUSF).
Gomez operations manager Stephen Corrow attributed the cost cutting to a “volatile” construction market, and city public works project manager Kristi Fries described the contractor's effort to stay within budget as “Herculean” (WUSF).
What Is Being Built
The memorial will occupy about 0.9 acres at 1912 S Orange Avenue in City Council District 4. Planned elements listed by the city include an Angel Ellipse, a private gathering area, a reflecting pool, a fountain wall, a prism tower, a visitor pavilion, parking, and landscaping, hardscape, site improvements and supporting infrastructure (City of Orlando). The reflecting pool sits where the nightclub's dance floor was, and the city says the flowing water represents “the non-linear movement of grief.” An advisory committee made up mostly of survivors and victims' families led the design process (WUSF). The plan also includes a visitors center and two survivor walls (WUSF).
Where Things Stand
The nightclub building was demolished in March and the Pulse sign was removed and preserved (WUSF). In October, the city said construction would start November 25 with site grading and tree removal, and that work was scheduled to finish by the end of 2027. Planners had earlier expected a September start, but the completion target did not change (WUSF). The city's project page lists a 12 month duration, with an anticipated start in the third quarter of 2026 and completion in the third quarter of 2027 (City of Orlando). The November 10 update did not give a revised completion date (WFTV).
Political timing is part of the backdrop. Mayor Buddy Dyer and Commissioner Patty Sheehan, whose district includes the site, both term out in January, and Dyer said they want to “make sure that that memorial is finished before we do.” Sheehan called the contract “the last step in the healing and the continuum of this process” (WUSF).
Background
Fundraising for a memorial was originally led by the nonprofit onePULSE Foundation, which faced accusations of misusing community and public money and dissolved in 2023. The city then bought the land (WUSF). Construction is beginning more than three years after that purchase (WUSF).
Implications for Owners, Developers, Contractors and Subs
The project is a small site with a demanding finish package: water features, a tower element, survivor walls and a pavilion on under an acre. The cost history shows how a public owner and a contractor held a fixed budget through design milestones by substituting materials and changing suppliers, a pattern familiar across Florida public work where budgets were set before recent price swings. Local suppliers picked up at least one package, the pavers, as part of that process. Subcontractors in lighting and electrical scopes should note that those trades were the ones still running over budget in October.
The site also sits on a busy commercial stretch. The city expects temporary road closures at the Kaley Street and Esther Street crossings, says businesses will keep driveway access throughout, and will post closure timelines before work begins (City of Orlando). That kind of public facing logistics plan is now standard for city managed work, much like the approach on other Central Florida projects such as the Coalition for the Homeless center in Orlando.
What to Watch
- Mobilization and the first visible site work, which the city expects this month.
- Whether the lighting and electrical overrun is closed without further scope changes.
- Posted closure schedules for Kaley Street and Esther Street.
- Whether the schedule holds for completion in 2027, ahead of or after the leadership transition in January.
Bottom Line
Pulse memorial construction in Orlando is moving from contract to site work, with Gomez Construction mobilizing on a $12.6 million budget that was held through extensive value engineering. Completion is targeted for 2027, and the city will post progress updates at PulseOrlando.org (WFTV).
Key Questions
When does Pulse memorial construction start?
The City of Orlando said on November 10, 2026 that construction activity at the Pulse memorial site is expected to become visible in November, after a notice to proceed was issued October 13 (WFTV).
Who is building the Pulse memorial in Orlando?
Gomez Construction, a Winter Park based firm, holds the $12.6 million contract approved unanimously by the Orlando City Council in October 2026 (WUSF).
How much does the Pulse memorial cost and who is paying?
The budget is $12.6 million. The City of Orlando budgeted $7.5 million, Orange County pledged $5 million and the Florida Legislature awarded more than $394,000, with private donors also contributing (WUSF).
When will the Pulse memorial be finished?
Completion is expected in 2027. The city's project page lists the third quarter of 2027, while earlier reporting cited the end of 2027 (City of Orlando).
Related Coverage
- Coalition for the Homeless Orlando Breaks Ground on 105,000 SF Center
- Florida Lands $416M in Federal Rail Funds for 910 Grade Crossings and a Brightline Cocoa Station
- Construction Partners Buys Palm Coast's S.E. Cline Construction
Image credit: City of Orlando. Image from the source article, City of Orlando.
Sources
- WFTV, “Construction activity expected at Pulse memorial site this month, Orlando says,” https://www.wftv.com/news/local/construction-activity-expected-pulse-memorial-site-this-month-orlando-says/JZJCNJLOIVC4JJBSOMRJM6PR2Q/
- WUSF, “Construction of Pulse memorial begins this month,” https://www.wusf.org/local-state/2026-11-12/construction-of-pulse-memorial-begins-this-month
- WUSF, “Orlando City Council approves Pulse memorial construction contract,” https://www.wusf.org/local-state/2026-10-13/orlando-city-council-approves-pulse-memorial-construction-contract
- City of Orlando, “Pulse Memorial Construction,” https://www.orlando.gov/Building-Development/City-Projects/Pulse-Memorial-Construction