Cortez Bridge Replacement Starts: $123M Span to Anna Maria Island

Cortez Bridge drawbridge in Manatee County, Florida, with both spans raised for boats | Westside Construction Group
Cortez Bridge drawbridge in Manatee County, Florida, with both spans raised for boats | Westside Construction Group

The Cortez Bridge replacement in Manatee County moved into active construction this week, as the Florida Department of Transportation said work on the $123 million fixed span bridge between Cortez and Anna Maria Island would get underway Monday, November 16, 2026 (Your Observer). Drivers should expect periodic daytime and nighttime lane closures, temporary traffic shifts and shoulder closures as crews begin pile driving and utility work along Hunters Point (Your Observer).

What Happened

The new crossing replaces the Cortez Bridge, a drawbridge that has connected Bradenton Beach on Anna Maria Island to mainland Manatee County since 1956 (Tampa Bay Business & Wealth). The replacement is a taller fixed bridge that boats can pass beneath without stopping traffic, with two travel lanes, wider shoulders and sidewalks on both sides (Tampa Bay Business & Wealth). The work covers nearly a mile of Cortez Road, from Gulf Drive in Bradenton Beach to 123rd Street West on the mainland (Tampa Bay Business & Wealth).

The Anna Maria Islander reported the new span will have 65 feet of clearance and 10 foot shoulders, and that SEMA Construction Inc. is the bridge contractor (The Anna Maria Islander). Your Observer described the replacement as 60 feet tall (Your Observer); the difference may reflect how height and clearance are measured, and FDOT's plans govern.

How the Work Is Staged

Crews will build the new bridge in two stages so drivers can keep crossing throughout construction, starting with the northern half alongside the existing drawbridge (Tampa Bay Business & Wealth). Traffic is expected to shift onto that new section in mid 2028, after which the old bridge will be torn down and the southern half built (Tampa Bay Business & Wealth). Barges and temporary platforms will let crews work over the water (Tampa Bay Business & Wealth).

The first visible changes come at the bridge ends, where traffic shifts slightly south so crews can relocate utilities and build a new connection to Hunters Point Way (Tampa Bay Business & Wealth). Early site work includes traffic control devices, mobilizing equipment and barges, pile driving from the water and roadway improvements near the approaches, and pedestrians are routed to the south side while crews work on the north side (The Anna Maria Islander). The drawbridge remains open to traffic during construction (The Anna Maria Islander).

Staging Site and Side Benefits

Manatee County approved a 60 day agreement on June 16 letting SEMA use portions of the county owned former Seafood Shack property at 4110 127th Street West in Cortez while staff negotiated a four year arrangement (The Anna Maria Islander). In exchange, SEMA will build a fueling station and parking area for the sheriff's marine unit and the Gulf Islands Ferry, repair sheet pile walls damaged during Hurricane Milton and build a bypass road connecting 127th and 126th Streets West (The Anna Maria Islander). County communications coordinator Ogden Clark said the site would affect fewer owners and businesses than land on the south side of Cortez Road (The Anna Maria Islander).

Schedule

Sources differ on duration. Tampa Bay Business & Wealth put the full project at about three years (Tampa Bay Business & Wealth), while The Anna Maria Islander reported construction would run about four years (The Anna Maria Islander). The mid 2028 traffic switch to the new northern half is the next firm milestone (Tampa Bay Business & Wealth).

The design reflects years of local input. A 2019 decision set the drawbridge's replacement with a taller crossing, and since 2020 a local committee has recommended four pedestrian overlooks, lighting beneath the bridge and railings with a wave pattern, features that could still change (Tampa Bay Business & Wealth).

Implications for Owners, Developers, Contractors and Subs

  • Marine and heavy civil work. Pile driving from the water, barges and temporary platforms put the early scope with marine construction and foundation specialists (The Anna Maria Islander).
  • Access planning. Businesses and contractors working on Anna Maria Island should plan deliveries around nighttime and daytime lane closures through the first phase (Your Observer).
  • Utility relocation. Relocating utilities at both ends is front loaded work for utility and site subcontractors (Tampa Bay Business & Wealth).
  • Regional pipeline. The bridge joins other Gulf Coast public work such as the agenda items in our Sarasota and North Port building votes roundup.

What to Watch

Bottom Line

The $123 million Cortez Bridge replacement is now under construction, with SEMA Construction building a high fixed span in two phases so traffic keeps moving. Expect lane closures, marine work and utility relocation first, with the first traffic switch planned for mid 2028.

Key Questions

When does construction on the Cortez Bridge start?

FDOT said work on the $123 million Cortez Bridge replacement between Cortez and Bradenton Beach would get underway Monday, November 16, 2026 (Your Observer).

Who is building the new Cortez Bridge?

SEMA Construction Inc. is the contractor for FDOT's Cortez Bridge replacement and is staging at the county owned former Seafood Shack property in Cortez (The Anna Maria Islander).

How long will the Cortez Bridge replacement take?

Tampa Bay Business & Wealth reported about three years and The Anna Maria Islander about four years for the Cortez Bridge replacement, with traffic moving onto the new northern half in mid 2028 (Tampa Bay Business & Wealth).

Will the Cortez Bridge close during construction?

No full closure is planned; FDOT is building the new Cortez Bridge in two stages so drivers can keep crossing, though periodic lane and shoulder closures are expected (Your Observer).

Related Coverage

Image credit: Tampa Bay Business & Wealth. Image from the source article.

Sources

Share

Let's connect

For organizations planning commercial, industrial, or infrastructure work, we will review the project and recommend the appropriate delivery approach.

Join our team

If you hold yourself to careful, accountable work, you already work the way we do.