Propel NY Energy Clears Construction Plans, Names Contractors

Propel NY Energy transmission project route map across Long Island, Queens, the Bronx and Westchester | Westside Construction Group
Propel NY Energy transmission project route map across Long Island, Queens, the Bronx and Westchester | Westside Construction Group

Propel NY Energy construction plans are approved, and the project has named the contractors and cable suppliers who will start the work. The New York State Public Service Commission approved the Phase 1 and Phase 2 Environmental Management and Construction Plans for the 90 mile underground and submarine transmission line on Thursday, November 19, 2026, and on Friday, November 20, New York Transco and the New York Power Authority announced Burns & McDonnell, The Crossing Group, LS Cable & System and Taihan among the firms selected for initial construction (NYPA). Pending additional approvals, site work at discrete locations along the route is expected to begin early next year (NYPA). This is a developing story.

What Happened

Propel NY Energy is a joint project of New York Transco and NYPA that will run roughly 90 miles of underground and submarine electric transmission through parts of Long Island, Queens, the Bronx and Westchester County (NYPA). The developers have described it as a $3.26 billion project (T&D World). Its purpose is to improve the reliability, resiliency and capacity of the state grid, particularly the links between Long Island, New York City and the rest of the state (NYPA).

The approvals cleared on November 19 cover the first two of several construction plans. Environmental Management and Construction Plans, known as EM&CPs, are a required part of the state permitting process and spell out how the project will be built in compliance with applicable laws and the conditions the PSC attached when it approved the project permit on September 17 (NYPA). Because of the project size, multiple EM&CPs will cover different regions and scopes of work, and the developers said contractors for later phases will be announced when procurement for those phases is complete (NYPA).

The timing followed a separate report from the state grid operator. The New York Independent System Operator released its 2026 Reliability Needs Assessment the day before the PSC vote and found that Propel NY Energy will provide significant benefits to statewide resource adequacy and reliability (NYPA). According to Talk of the Sound, the NYISO report found that without the project, Long Island could see transmission reliability deficiencies as early as summer 2030, and a projected statewide resource deficiency would arrive a year sooner and be about 550 megawatts larger (Talk of the Sound).

What Is Confirmed

Phase 1: Long Island Substations

The Phase 1 plan covers vegetation management at the Long Island substation sites. It was first filed on June 22, 2026, and refiled with agency and public comments on October 9 (NYPA). Burns & McDonnell was selected as prime contractor for the three new Long Island substations, at Shore Road, Ruland Road and Barrett, which will be built on existing utility owned property next to existing stations (NYPA). Haugland Group and Hitachi Energy will serve as key subcontractors, and the project has already bought critical long lead equipment from SGB-SMIT Group and Hitachi to protect its schedule (NYPA).

Phase 2: Landfall Drilling

The Phase 2 plan covers horizontal directional drilling at the two landfall locations that will receive the submarine cable crossing Long Island Sound. It was first filed on July 10 and refiled on October 16 (NYPA). The Crossing Group will perform the trenchless crossings for the New Rochelle to Glen Head landfall, working with Hallen Integrated Construction Services (NYPA). Talk of the Sound reported that the New Rochelle landfall is at the Hudson Park and Beach parking lot, and that the Long Island end is at Shore Road in the Town of Oyster Bay (Talk of the Sound).

Cable Supply

LS Cable & System and Taihan were selected to supply the terrestrial cable and will work with local contractors to install and splice it. LS Cable & System will also supply and install the submarine cable (NYPA). LS Cable Systems America said its scope includes 345 kV high voltage cable systems for both the submarine and underground segments (NYPA).

Schedule and Jobs

More active construction is expected to start in mid-2027. Work will proceed in segments and phases, with multiple crews working at different locations at the same time, to deliver the project in 2030 (NYPA). The developers estimate the project will support about 2,000 jobs a year over an anticipated four year construction period and add about $2.4 billion to the local and regional economy (NYPA). They also said the selected firms are committed to employing a skilled union workforce (NYPA).

What Is Not Yet Known

The first two approvals do not cover all of the work. Additional plans must still be approved for the transition vaults, the submarine cable and other portions of the system (Talk of the Sound). The exact start dates by location are also unclear. Talk of the Sound noted that the Phase 2 fact sheet lists drilling windows at Hudson Park from November 2026 through April 2027 and again from November 2027 through April 2028, while the November 20 announcement points to an early 2027 start; the outlet said it has asked New York Transco to clarify (Talk of the Sound). The publicly released fact sheet also does not say how many parking spaces will be lost or how long beach and marina access might be affected (Talk of the Sound). Contract values for the individual awards were not disclosed.

This is a big step from where the project stood in June, when the developers picked Hallen, Haugland Group and BOND Civil & Utility Construction to help with value engineering and regulatory filings during the permitting phase (T&D World). Two of those firms now appear in construction roles.

What It Means for Owners and Contractors

  • Substation and civil packages are moving first. With Burns & McDonnell leading three new substations, the next wave of opportunity on Long Island will be in site work, foundations, grounding, duct banks, fencing and electrical installation under the prime. Firms that want that work should be talking with the prime and its named subcontractors now.
  • Underground cable work will need local crews. The cable suppliers will rely on local contractors to install and splice cable (NYPA). That points to trenching, duct bank, manhole and vault construction, paving restoration and traffic control along the land route, much of it in dense suburban and urban streets.
  • Long lead equipment is already committed. The developers procured critical long lead equipment early to hold the schedule (NYPA). Owners planning their own substation or service upgrades in the region should expect continued competition for the same gear and trades, a pressure we have tracked in coverage of Niagara Power Transformer’s Cheektowaga expansion.
  • Union labor is part of the plan. The developers have stated their commitment to a skilled union workforce (NYPA), which affects how open shop firms can participate.
  • Grid capacity remains a gating item for growth. Developers of large loads on Long Island and in the New York City area should note the NYISO finding that delays to this line would bring reliability shortfalls forward (Talk of the Sound).

Propel NY Energy is one of several large grid and energy programs moving through New York this fall, alongside the state’s $228 million in port infrastructure awards announced the same day, in which Haugland Group is also a development partner.

What to Watch

  • Clarification of the Hudson Park drilling start date and any site mobilization notices.
  • PSC filings and approvals for the remaining EM&CPs covering the transition vaults, submarine cable and land route.
  • Contractor announcements for later phases once procurement closes (NYPA).
  • The quarterly project webinar on December 15 at 6 p.m., where the developers plan to present updates and new public tools including an interactive construction map and a 24 hour hotline (NYPA).

Key Questions

What did the PSC approve for Propel NY Energy?

On November 19, 2026, the New York State Public Service Commission approved the Phase 1 and Phase 2 Environmental Management and Construction Plans for Propel NY Energy, covering Long Island substation site preparation and horizontal directional drilling at the two Long Island Sound landfalls (NYPA).

Who are the Propel NY Energy contractors?

Burns & McDonnell is prime contractor for three new Long Island substations, with Haugland Group and Hitachi Energy as key subcontractors; The Crossing Group and Hallen Integrated Construction Services will handle landfall drilling; LS Cable & System and Taihan will supply cable (NYPA).

When will Propel NY Energy construction start?

Pending additional approvals, NY Transco and NYPA expect site work at discrete locations to begin in early 2027, with more active construction in mid-2027 and completion in 2030; exact start dates at Hudson Park in New Rochelle are not yet confirmed (Talk of the Sound).

How much does Propel NY Energy cost?

Propel NY Energy has been described as a $3.26 billion, 90 mile underground and submarine transmission project across Long Island, Queens, the Bronx and Westchester County (T&D World).

Related Coverage

Image credit: Propel NY Energy project map, via T&D World. Image from the source article.

Sources

Share

Let's connect

For organizations planning commercial, industrial, or infrastructure work, we will review the project and recommend the appropriate delivery approach.

Join our team

If you hold yourself to careful, accountable work, you already work the way we do.