Westside Construction Group completed a comprehensive renovation at Cleveland Hill High School in Cheektowaga, NY. Our scope included demolishing an outdated snack shelter, pouring a new footer with high subsurface compaction, and installing an ADA-compliant ramp from the parking-lot sidewalk into the building. Every step prioritized safety, durability, and accessibility for students and staff.
Remove the existing shelter without damaging adjacent walkways or landscaping, using specialized tools and dust-control measures.
Pour a reinforced concrete footer engineered for 98% soil compaction, establishing a stable base for the new shelter.
Form and finish a ramp meeting all ADA slope, width, and landing requirements to provide barrier-free access.
Conduct regular in-field compaction tests to verify 98% density, ensuring long-term structural integrity under foot and vehicle loads.
Adhere to local building codes and ADA standards throughout demolition, formwork, and finishing operations.
Restore all disturbed areas—including lawns, walkways, and parking edges—to pre-project condition, leaving the campus neat and safe.
The Cleveland Hill High School project showcases Westside Construction Group’s commitment to precision, safety, and accessibility. From tear-down to ramp-finish, we delivered a durable footer and ADA ramp—complete with rigorous compaction testing and site restoration—ensuring students and staff enjoy a safer, more inclusive campus environment. For turnkey construction solutions that never compromise on quality or compliance, contact Westside today.
Remove an aging snack shelter and pour a reinforced footer with 98% compaction, then install an ADA-compliant ramp—ensuring both a stable foundation for the new structure and barrier-free access for all campus users.