NYC Transit Expansion: Hochul Pushes Multiple Megaprojects Including $7.7B Second Avenue Subway Extension

Westside Construction Group
Building Better Blogs.

New York Governor Kathy Hochul is championing an aggressive slate of major mass transit expansion projects that could represent New York City's most ambitious infrastructure push in nearly a century. Her vision includes extending the Second Avenue Subway west across Manhattan, building the Interborough Express light rail line connecting Brooklyn and Queens, and advancing Metro-North service to the West Side of Manhattan through the Penn Access project.

Second Avenue Subway Extension Plans

Governor Hochul announced in her January 2026 State of the State address that the MTA will explore extending the Second Avenue Subway westward from its planned 125th Street terminal, potentially adding three new stations beneath Broadway and connecting through multiple neighborhood crossings.

Key expansion details:

  • Phase Two scope: $7.7 billion, three-station extension from 96th Street to East Harlem
  • New westward extension: Potential stations at Lenox Avenue, St. Nicholas Avenue, and Broadway
  • Tunnel boring approach: One-half to full-length tunnel boring machine already approved for $1.9 billion contract
  • Potential savings: Preserving the bore opportunity could save hundreds of millions by continuing west rather than abandoning tunnels
  • Community impact: Would replace the slow crosstown M125 bus, the most important transit route between 53rd Street and Fordham Road

The crosstown service currently experiences severe congestion and delays on bus transit. A proposed subway line could eliminate bus transfers for large numbers of commuters and significantly reduce travel times across Manhattan's 125th Street corridor.

Interborough Express Light Rail Line

The Interborough Express (IBX) represents the most ambitious transit construction since the IND Crosstown Line (now the G train) fully opened in 1937.

IBX Project Details:

  • Total scope: 19-station light rail line
  • Capital cost: $5.5 billion
  • Route: Jackson Heights, Queens to Bay Ridge, Brooklyn
  • Infrastructure: Built on existing freight rail corridor
  • Current status: Early engineering and design phase, funding not yet complete
  • Expected service: End-to-end transit route between two boroughs, eliminating multi-borough transfers

Governor Hochul backed the IBX early in planning, signaling state support for this transformative project.

Metro-North Penn Access to West Side Manhattan

The Penn Access project would extend Metro-North commuter rail service from the Hudson and Harlem rail lines directly to Manhattan's West Side through Penn Station, creating new commuter connections.

Penn Access Components:

  • Four new commuter rail stations in The Bronx
  • Direct Manhattan connection to West Side Penn Station
  • Service expansion: Metro-North westbound capacity
  • Regional benefit: Improved access from Hudson Valley and Bronx communities

Jamaica Station Integration Project

Governor Hochul also announced that the MTA will pursue design work on a reimagined Jamaica Station complex that would better integrate multiple transit modes.

Jamaica Station improvements would coordinate:

  • Subway service connections
  • Long Island Rail Road (LIRR) access
  • AirTrain to JFK Airport
  • Bus terminal facilities

Better integration would eliminate confusing transfers and reduce travel times for millions of annual Jamaica Station users.

Hochul's Infrastructure Legacy

Governor Hochul, a Buffalo native, is building a transportation legacy that could benefit New Yorkers for generations. Her approach differs notably from the congestion pricing pause controversy of 2024.

Hochul's transit accomplishments include:

  • Congestion pricing implementation: $15 toll south of 60th Street generating new MTA revenue (Jan. 2025 marked one-year anniversary)
  • Budget stability: Prevented MTA fiscal cliff that threatened service cuts and fare increases
  • Capital investment: Funded both transit operations and major expansion projects simultaneously
  • LIRR expansion: Completed nearly 10-mile third track on Long Island in 2022
  • Recent megaproject success: L line Sandy repairs completed on time in 2020; LIRR third track and East Side Access showing strong completion records

Federal Funding Challenges and Trump Administration Concerns

The ambitious expansion plans face significant financial hurdles. President Donald Trump has threatened to withhold federal funding from Phase Two of the Second Avenue Subway, raising concerns about multi-year project viability.

Key funding challenges:

  • Phase Two Second Avenue Subway: $7.7 billion (in planning stages)
  • Interborough Express: $5.5 billion (early design, not yet fully funded)
  • Second Avenue West extension: Design costs to be revealed by Hochul this week
  • Federal government appetite uncertain, especially post-2024 election

Historical Context: Learning From Past Transit Megaprojects

The MTA has faced criticism for expensive, slow construction on previous megaprojects. The first phase of the Second Avenue Subway earned the infamous 2017 New York Times label: "Most Expensive Mile of Subway Track on Earth."

However, MTA Chair Janno Lieber argues the authority has improved project delivery:

  • LIRR third track expansion: On time, under budget
  • L line Sandy repairs: Completed 2020 on schedule
  • East Side Access: LIRR terminal beneath Grand Central near completion
  • Current credibility with governor and public: Improved based on recent project track records

Why This Matters for Construction and Real Estate

These major transit expansions create enormous economic opportunities for New York's construction and development sectors.

Construction Industry Impact: Multiple megaprojects will generate years of employment in design, engineering, tunnel boring, station construction, and related trades. The estimated $20+ billion in combined project costs will support construction workers, equipment operators, engineers, and project managers.

Real Estate Development: Transit-oriented development around new stations will attract commercial and residential investment. Neighborhoods along proposed routes—Jackson Heights, Harlem, Bay Ridge, Jamaica—could see increased property values and development interest.

Long-term Transportation Benefits: When completed, these projects will reduce traffic congestion, shorten commute times, and attract workers and businesses to transit-served areas.

Regional Economic Growth: Improved transit connections strengthen economic links between boroughs and regions, attracting corporate headquarters and workforce talent.

Next Steps and Timeline

The MTA will begin preliminary engineering and design work on the Second Avenue Subway westward extension. Governor Hochul will reveal anticipated design costs for the 125th Street extension this week. The Interborough Express and Penn Access projects will continue advancing through design phases while seeking federal and state funding.

With Hochul showing strong political support, the MTA positioning itself as a capable project manager, and the infrastructure investment imperative clear, these megaprojects appear positioned to move forward—though federal funding remains a significant wildcard.

Industry Insight: Westside Construction Group recognizes the importance of major transit infrastructure for regional economic development. WCG's experience on complex construction projects across Upstate New York provides expertise in managing large-scale transportation and infrastructure improvements. For consultation on transit-oriented development or major infrastructure projects: (585) 440-0304 or www.buildwcg.com

Read us in socials:
Social iconSocial iconSocial icon
Our latest articles

Latest industry news

Jan 31, 2026
New York Budget Allocates $300M for Rochester Monroe County Development

Governor Hochul allocates $300M for Monroe County/Rochester in 2027 state budget. $225M for Rochester-Monroe Transformation Initiative, $75M for High Falls State Park. Aims to drive job creation and economic development.

Jan 31, 2026
Sydor Optics Acquires Vertex, Plans 100K Sq Ft Rochester Expansion 2027

Rochester optics manufacturer Sydor acquires Vertex Optics, doubles capacity with 100,000-sq-ft facility expansion. New plant opens summer 2027, construction begins spring 2026. First acquisition in company history.

Jan 31, 2026
Reju Opens $390M Textile Regeneration Hub at Eastman Business Park Rochester

French company Reju launches $390M textile-to-textile regeneration hub at Eastman Business Park in Rochester. 145,000-sq-ft facility will recycle 300M clothing items annually, creating 70 jobs.

Build with confidence—
start your project with us today.

Text Rotate